試卷名稱(chēng) 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線(xiàn)考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the project’s execution, the project manager realizes that key stakeholders are missing from the stakeholder register. What technique should have been used at the beginning of the project to prevent this from occurring ?
A、Update stakeholder register.
B、Conduct stakeholder analysis.
C、Define stakeholder management strategy.
D、Identify stakeholders.