試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During project execution, an important stakeholder, who is a capital investor in the client’s business, disagrees with a significant scope item. What should the project manager do ?
A、Advise the stakeholder that it is too late to change the scope
B、Agree to the scope change with the stakeholder
C、Apply the changes management plan for the stakeholder’s scope
D、Terminate the project because the scope is not aligned with the client’s business